Can a Hotel Stay Open During Refurbishment?

Closing a hotel for six months means six months of no revenue, so most owners want to trade through their refurbishment. It can be done, and it is done every week across Manchester and the North West, but it needs proper phasing, honest guest communication and a contractor who understands that a live hotel is not a building site. Here is what actually works.

Published 6 September 2026

When trading through works and when it does not

Staying open makes sense when the work is largely room-by-room or floor-by-floor: bedroom refits, bathroom replacements, corridor redecoration or a lobby refresh. A 120-room hotel can typically take 20 to 30 rooms out at a time and keep the rest selling, which means the programme stretches over four to six months rather than eight to ten weeks, but the trading loss is far smaller.

Closure is usually the better choice when the work touches the building's core systems. Replacing a lift, rewiring risers, renewing the main sprinkler or fire alarm system, or structural alterations to the ground floor are hard to isolate safely. Full closure also tends to win when the kitchen or the only bar and restaurant is coming out, as guests lose the reason to book.

A useful test is to ask whether a guest who has paid full rate could arrive, sleep, eat and leave without noticing the works beyond a polite notice. If the honest answer is no, a short closure or a discounted soft-trading period is often less damaging than a run of poor reviews.

Phasing the works around occupancy

Most Manchester hotels trade hardest Thursday to Sunday and during conferences, football fixtures and arena events. The sensible pattern is to programme noisy work such as demolition, drilling and tile removal for Monday to Thursday, between roughly 9am and 5pm, and to keep Fridays and weekends for quiet finishing trades like decorating and snagging.

Rooms should be blocked in vertical stacks where possible so one riser and one corridor section is isolated at a time. Taking a whole floor out means hoardings can go up at the lift lobby and the fire stairs, guests are never routed past open works, and housekeeping can drop that floor from their rota entirely.

Build in a buffer. If the programme says a block of rooms returns on the Thursday before a big weekend, do not release them for sale until the Friday. Cutting it fine is how you end up walking a guest to a room that still smells of paint.

Fire safety, insurance and the legal side

Refurbishment in an occupied hotel changes the fire risk, and the Regulatory Reform (Fire Safety) Order 2005 puts the duty on the responsible person to reassess it. That normally means a revised fire risk assessment before works start, temporary fire stopping wherever compartment walls are opened, and a hot works permit system for any cutting, welding or soldering.

Fire alarm zones under construction are often isolated to stop dust triggering false alarms. Where that happens, the contractor should provide temporary detection or a fire watch, and the evacuation plan and staff briefings must be updated to reflect any stairs or exits that are out of use. Greater Manchester Fire and Rescue Service can and do inspect hotels during works.

Tell your insurer before the works begin. Many policies require notification for contracts above a stated value, often around £50,000 to £100,000, and an unannounced refurbishment can void cover. Check the contractor's public liability cover, usually £5 million to £10 million for this type of work, and agree in writing who insures the works themselves under the building contract.

Keeping guests happy while the builders are in

Honesty at booking stage is worth more than any discount afterwards. A short line on the website and booking confirmations, saying which areas are affected and during what hours, cuts complaints dramatically. Guests who feel ambushed on arrival write reviews. Guests who were told in advance mostly shrug.

Practical steps matter too. Put guests as far from the works as the building allows, offer a small gesture such as a late checkout or a drink for anyone placed near an affected area, and give reception a plain script for handling noise complaints. Daily briefings between the site manager and the duty manager, even five minutes over coffee, stop most problems before they reach a guest.

Expect a modest dip in average rate during the works, commonly 5 to 15 percent on affected floors, and factor it into the business case. The upside is that refurbished rooms in Manchester typically command a noticeable premium once they are back on sale, so the earlier finished rooms are released, the sooner the project starts paying for itself.

What to ask your contractor before signing

A contractor who has only ever worked on closed sites will struggle in a live hotel. Ask for examples of occupied refurbishments they have delivered, how they managed deliveries through a working loading bay, and what their noise and dust controls actually consist of. Ask whether they will provide a dedicated site manager who is on site every day and who your duty manager can reach.

Agree the working hours, the phasing plan and the guest-facing rules in the contract, not in conversation. Most live hotel refurbishments in the North West run under a JCT Intermediate or Design and Build contract with a schedule of restrictions attached, covering hours, noise limits, protected routes and handover standards for each phase.

Frequently asked

Common questions, plainly answered

Typically 40 to 80 percent longer, so a job that would take ten weeks in an empty building might run four to five months while trading. The extra time comes from restricted hours, smaller work areas and the discipline of handing back rooms in finished blocks.

There is no specific legal duty to warn every guest, but under consumer law a room materially affected by noise or lost facilities may not be what they paid for. Telling people at booking stage is both the honest approach and the best protection against refund claims and poor reviews.

Often yes, if the works are confined to bedrooms and corridors. If the kitchen itself or its extract and gas supply are being replaced, a short closure of food service, or a temporary limited menu, is usually safer than trying to cook around builders and environmental health requirements.

Related

More from Prometheus

Start a conversation

Tell us about your site or scheme

Tell us about your site or scheme and we will come back with a route to delivery, whatever stage you are at.

Call usLoading…
WhatsAppMessage us
BaseManchester · serving Leeds & London
HoursMon to Fri 08:00 to 18:00 · enquiries anytime

We reply within one working day. No obligation.